Hi Julie,
Thanks for your help I have read the other comment and I have
looked
on the
website. I understand the basic aim but having real trouble
figuring
out the
formula which will indicate the differing tolerance levels.
Sorry but I am really computer illiterate please help!
Quirky
:
Hi Quirky,
You're welcome and thanks for the feedback.
I see you have posted your new question as a new thread and it
looks
as
though Mike has given you some guidance.
If you have any follow up questions, go ahead and reply to your
latest
post and we'll pitch in again
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
Thanks Julie,
Sorry for the delay in replying but I have only just found the
time
to
implement this change! It worked perfectly thank you...
I am happy with this column but would like to add to it. I was
wondering if
you knew how I could build in my defined quality and reporting
tolerance
levels.
For example, I have tolerance levels of 5% over budget and
schedule
overrun
and would like these indicated red. Similarly I also have a 10%
under
budget
and ahead of schedule reporting criteria. I would like these to
be
marked
green. For the remaining tasks I would like these to appear
amber
to
signify
that they are same as baseline or within tolerance levels.
Do you or anyone else have any ideas to my problem?
Quirky
:
Hi Quirky,
Insert a Text field (Text1 for example) and customize the field
with
the
following formula:
Switch([Start]<=ProjDateAdd([Current
Date],9600),"Soon",[Start]>ProjDateAdd([Current Date],9600) And
[Start]<=ProjDateAdd([Current Date],19200),"Next
Month",[Start]>ProjDateAdd([Current Date],19200),"Future")
The formula should show "Soon" for any task that starts within
the
next
20 working days. The formula should show "Next Month" for
tasks
that
start between 21 days and 40 working days from today's date.
The
formula should show "Future" for any tasks that starts more
than
40
days
from today's date.
You can modify the measurements used (20 days, 40 days) as
needed --
just remember that the formula adds minutes -- hence the need
to
multiply all values by 480 (8 hours * 60 minutes)
Then select the Graphical Indicators button in the Customize
fields
dialog box. Use the following tests:
Row 1
Text1 equals Soon - green indicator
Text1 equals Next month - yellow indicator
Text1 equals Future - red indicator
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
I am trying to Flag tasks using Traffic light system to
highlight
what
Tasks
are about to start (ie Green) what tasks are due to start in
1
Month
(amber)
and What Tasks are due to start in 3 Months (Red).
However finding it hard to understand what formula is needed
to
make
this
happen?
Any suggestions????