Jon said:
I am holding a meeting for 1 hr. How should I create this
task, by saying it is 1 day with 13% units fixed Duration.
Or should I load it with 1h with 100% units fixed duration.
thx
jon
If your schedule is more than a few weeks I would not even bother entering
it. Afterall, do you have lunch scheduled? How about coffee breaks?
There is a certain point where making your schedule model more complex stops
helping you and begins to become a burden. For me, I'd say that scheduling a
1 hour meeting falls on the far side of that point. Make your schedule as
simple as possible and no more so.
--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check
http://masamiki.com/project
-Jack Dahlgren, Project MVP
+++++++++++++++++++