Hours in Portfiolio Analyser not adding up

C

Chris Walsh

If i design a report for the Work Hours and Avibality Hours for the entire resource pool all resources avability are the same, even though their already booked out 85% of the time????
 
J

James

Hi Chris,

Maybe someone more knowledgable than me can confirm this, but I think
Availability means Total Availability and not remaining availability which
is what I think you are looking for. Therefore Availability is not affected
by existing commitments other than holidays/non working days etc...

Regards

James


Chris Walsh said:
If i design a report for the Work Hours and Avibality Hours for the entire
resource pool all resources avability are the same, even though their
already booked out 85% of the time????
 