How can I change the working day ?

A

abby

If I don't connect to the project server , I can change
the working day in the tools---change working day
But if I connect to the project server , when I open a
project ,the dialog box of change working day can't be
used.

The role of logging in is administrator.

Thanks,
 
D

Dale Howard [MVP]

Abby --

If you are logging in with administrator permissions, it sounds like someone
has set the Change Working Days permission to Deny in one of the Groups to
which you belong. If a permission is set to Deny in one of your Groups, and
is set to Allow in all of your other Groups, the Deny permission will always
"trump" the Allow permission. Alternately, one of your Project Server
administrators may have set the Change Working Days feature to Deny in the
features grid found on the Server Configuration page in PWA. Hope this
helps.
 
A

abby

Dale:
Thank you for your answers.
Now I'm logging in with administrator permissions and
administrators group is the only group I belong to.
I check the set on the Server Configuration page in PWA,
the Change Working Days feature is permit in the features
grid.

On the other hand, When I open the dialog box of the
Change Working Days, in standard calendar Option, I can't
change the working day. But I can set up a new calendar in
this page, but I don't know how to apply this calendar to
the project.

Can you give me some suggestiones?
Thanks a lot.
 
D

Dale Howard [MVP]

Abby --

You need to open the Enterprise Global before you can change or create
enterprise calendars. Click Tools - Enterprise Options - Open Enterprise
Global, then click Tools - Change Working Time. Hope this helps.
 
K

K Treston

When connecting to the project server, first open the Enterprise Global then
make the change.

K Treston
 