how can i extract only certain tasks from project

D

dominic

I have a master project plan, I want to create a new one with just all of the
task that say alaph testing, beta testing.
 
G

Gérard Ducouret

Hello Dominic,
First : create a filter which'll test on a constant word such as "testing":
Project / Filter for / More filters / Create
- Field name : Name
- Contains
- Value : testing
Apply the filter
Select all : click the gray square at the upper left angle
Copy and paste in the other project

Hope this helps,

Gérard Ducouret
 