How can I hard code everything from an existing schedule?

E

EProject

Hey all,

I need to get inputs from someone, but due to the sensitive nature of the
information, I want to take out all the resources and work for tasks. But, I
still need the dates and durations to stay in the tasks so I can have it for
this person's input.

I tried making everything fixed duration, but when I "0" out the work, some
start dates change alittle.

Any help would be much appreciated!

Thank
 
E

EProject

Played around with it. I made everything fixed duration and Must Start On.
Erasing the resources and work seems to hold the dates.

Whew!
 