How can I make a report with baseline changes?

M

MarcosLima

Gentlemen

I have a project with a saved baseline.
After that, we have included some tasks and changed some durations.

Is there any way to list all those changes comparing to the baseline, eg,
included tasks and changed tasks?

Thanks
Marcos
 
R

Rod Gill

What doesn't the Tracking Gantt view show you that you need? Remember you
can insert extra baseline columns for duration and work etc. Tasks with no
baseline are new.
 
D

Dale Howard [MVP]

MarcosLima --

To add to Rod's excellent answer, you can also apply any of the Tables that
show you variance, such as the Cost, Work, and Variance tables. To do so,
apply any task View (such as the Gantt Chart view) and then click View -
Table - Cost (or Work or Variance). Hope this helps.
 
Top