B
Bev
Hello,
I need to run several tasks in parallel, how do I do that?
Thanks, cheers, Bev.
I need to run several tasks in parallel, how do I do that?
Thanks, cheers, Bev.
What if you want to tasks to occur simultaneously - I.e. an SS & FF together?
I want to represent the fact that test scripts need to be written at the same time as the detailed technical spec for system. however the test script task is a single task and the detailed technical spc has 30 sub tasks, each with a different predecessor.
Ideally I would like to link the test script task to the detailed technical spec header task by putting something like 85PA in the predecessor column (PA standing for Parallel) PA is a made up shortcut, but does anyone knowthe real abbrev for this action?...
Thanks!
- Show quoted text -