Hello Bev,
You've not given us much to go on -- so I'll toss out a few options.
When you create tasks, by default they will be scheduled for the
start date of the project. By creating links or predecessors and
successors, you will change the schedule for the task. So, if you
have several tasks which are a common predecessor, they will be
scheduled to occur at the same time. For example:
Task A is the Predecessor in a Finish to Start relationship with
both Task B and Task C. Because both Task B and Task C have a
Finish to Start relationship with Task A, they are both initially
scheduled to start on the same day.
A different scenario would be if you could not start Task B until
Task A was started -- then that would be a start to start
relationship.
Yet another scenario would be if you needed to ensure that Task B
did not finish until Task A finished -- that would be a Finish to
Finish relationship.
So, the short answer is you create parallel tasks by creating
predecessor and successor relationships that correctly express the
schedule you desire.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project