How do I allocate resources in Microsoft Project 2000?

J

JH

Is there a way to allocate resources automatically so that they alternate
tasks? i.e.
example:
Task 1 Worker 1
Task 2 Worker 2
Task 3 Worker 1
Task 4 Worker 2
etc.
 
J

JulieS

Hello JH,

Sorry, no. There is no "automatic" way of assigning of resources,
that is up to the person using Project. You certainly could
manually select every other task and then use the Assign Resources
dialog to assign the selected tasks to Worker1, then select the
other tasks and assign Worker2 with one click.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
Top