How do I assign workers with annual pay rather than by hour?

G

Gérard Ducouret

Zaira,

In the Std. Rate field of the Resource Sheet of Project, enter a value like
20000/y
where y stands for "year".
Hope this helps,

Gérard Ducouret
 