how do I change duration hours in project to days in existing dat

C

ChasBush

I have existing data and would like to change duration, total float etc into
days from hours.
 
J

JulieS

Hello ChasBush,

You can show the duration in a different format by running the
Format_Duration macro. Tools > Macro > Macros, select the
Format_Duration Macro and click the Run button. Select Days from
the dropdown.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 