How do I change Project 2003 timescale from week-beginning to wee.

M

Mack Real III

How do I change the Project 2003 timescale from week-beginning to week-ending
days...
 
M

Mike Glen

Hi Mack,

Welcome to this Microsoft Project newsgroup :)

I don't know if this will meet your need, but you could try changing the
setting: Tools/Options.../Calendar tab - Week starts on: .

Another possibility is to Format/Timescale.../Label and select W2,W1.. (From
End)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
M

Mack Real III

Hi Mike,

This doesn't quite get to the problem. When I set up my time scale I set the
Middle Tier to month and year ("November 2004"). Then I set the Bottom Tier
to days (which returns: 1,8,15,22,29). These are the week beginning days (all
of the Mondays). My boss has been keeping a schedule in Excel for years...
There in lies the problem. He has been using the week ending days (all of the
Fridays - 5,12,19,26). I don't know how to make Project 2003 do that.
 
Top