Hi Mike,
This doesn't quite get to the problem. When I set up my time scale I set the
Middle Tier to month and year ("November 2004"). Then I set the Bottom Tier
to days (which returns: 1,8,15,22,29). These are the week beginning days (all
of the Mondays). My boss has been keeping a schedule in Excel for years...
There in lies the problem. He has been using the week ending days (all of the
Fridays - 5,12,19,26). I don't know how to make Project 2003 do that.