I am seeking to set up a Project using non AM/PM time ie use 2400 hrs instead. Can this be done?
A Andrew Apr 26, 2009 #1 I am seeking to set up a Project using non AM/PM time ie use 2400 hrs instead. Can this be done?
R Rod Gill Apr 26, 2009 #2 Hi, Yes. Project uses whatever your Regional setting is in the Control Panel. So, go to the control panel and reset your default time format. No need to even close Project usually either, it just changes. -- Rod Gill Microsoft MVP for Project Author of the only book on Project VBA, see: http://www.projectvbabook.com
Hi, Yes. Project uses whatever your Regional setting is in the Control Panel. So, go to the control panel and reset your default time format. No need to even close Project usually either, it just changes. -- Rod Gill Microsoft MVP for Project Author of the only book on Project VBA, see: http://www.projectvbabook.com