How do I change the duration of an existing task?

S

stephanie_ww

I have a project plan that was created using duration of days and I want to
change the duration of existing tasks to weeks. I changed the default setting
for new tasks, so they're created using a duration of weeks, but can't figure
out how to change the duration of the tasks already set up from days to weeks.
 
J

JulieS

Hello Stephanie,

Run the Format_Duration macro through Tools >Macros > Macro. Select
weeks when prompted.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 