How do I change the Duration on a template in Project?

T

Tracy

Hi there,

I am new to Project so please bare with me!

I am trying to change the duration on a template. I have gone in
and changed the start and finish date however I can not seem to
change the duration.

Help!!!

Thanks !
Tracy
 
M

MrAlNather

Hi there,

I am new to Project so please bare with me!

I am trying to change the duration on a template. I have gone in
and changed the start and finish date however I can not seem to
change the duration.

Help!!!

Thanks !
Tracy

Have you got project calculation on manual...try pressing "F9" to find
out
 
E

Ellen Lehnert

Have you got project calculation on manual...try pressing "F9" to find
out

When you say "template" are you trying to change the template itself
(the .mpt file) or a copy of it that you are trying to use as a
schedule?

Also - the way the system works is that you enter your tasks, use
relationships to establish the order of the tasks, enter a duration
and the sytem will calculate the start and end dates. Plugging dates
is not a best practice of using MS Project.

The duration was calcuated so if you are trying to change the entire
project duration, it is not a field that could be changed. Go to
Project --> Project Information and change the start date.

Also - consider a good training class.

Good Luck

Ellen
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top