M
Mark said:Thank you Julie.
I will let you know what I come up with. As for my brain, I haven't seen it
since the directors introduced bean counting 401 (How to be 120% Productive
with no Incentives) (LOL).
Mark
Mark said:John,
No it won't. If I allow the program to update it that way I will not be
able to calculate budget with true percentage complete. If I update the
program to 10% complete it will automatically adjust my hours to match up.
Same with schedule. I need to know what the projected schedule is to
calculate where we are currently at. The cumulative hours is my baseline for
Schedule Performance Index.
Jan De Messemaeker said:Hi,
I can send a snippet calculating it on task level
subCumWork
dim Job as task
dim TSV as timescalevalues
For each job in activeproject.tasks
if not job is nothing then
job.number1=0
if not job.start>vba.date then
set tsv=job.timescaledata(job.Start,VBA.Date,pjtasktimescaledcumulativework,
_
pjtimescaledays,1)
Job.Number1=tsv(tsv.count)/(60*activeproject.Hoursperday)
end if
end if
next job
end sub
HTH
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.