I commonly utilise the "Task Entry" view when entering and reviewing tasks
and their resources, predecessors and successors. I know that there are a
number of views available in this "view" including resources & predecessors,
resources & predecessors, and predecessors & successors.

However, there seems to be sufficient space to add an additional table to
this form view so that resources, predecessors and successors could all be
visible at once. I don't know about anyone else but I would find this
layout extremely useful and the absence of this option seems to be an
obvious oversight.

Can anyone advise me if it is possible to customise this form/view and if so
how do I go about it?

Thanks

Jack
 
R

Rod Gill

Hi,

Tables define what columns are visible in all spreadsheet areas of Views.
So, select View, Table, More Tables and copy the table you like most, give
it a new name, then add/delete the relevant columns.

Apply the table in a Gantt or Task Sheet view whenever you want.
 