How do I handle multiple project locations?

M

Matt

In using MS Project Server 02'. I will usually have a location name followed
by a group of subtasks? When the server sends out the subtasks to the
resources it only shows the task itself, but not the tasks that it roll up
to, therefore they do not know what location it is for. What is a better way
to handle this?
 
D

Dale Howard [MVP]

Matt --

On each user's View My Tasks page in PWA, teach them to click the View
Options tab and to select the "Show summary tasks" option. Hope this helps.
 
G

Greg Horodeck

Put the location name in each subtask, each task name should stand on its
own without implicit reference.

In Project Professional views such as Resource Usage, you don't have the
Summary Task name to rely on.


Greg
 