M
MntnrMark
I have a 300 or so tasks schedule for a project. The client has told us they
want to insert a six-week delay in the middle of the project and want to see
the effect on all of the tasks. Basically, what I want to do is show that
six-week gap across all tasks at once without having to go into each
individual task, split each task, adjust the dates for each task and have to
manually figure how much time would be remaining on each task (as I'm hoping
the software can do that for me). For example, task 40 would be, say, two
weeks into a total six week duration when the delay takes effect, making the
total duration now two weeks of the task already completed plus the six week
delay plus the remaining four weeks of activity that would remain after the
delay ends, for a total duration now of twelve weeks. Is there a simpler way
to show this on the project as a whole rather than have to split each
individual task? Thank you for any assistance you can provide.
want to insert a six-week delay in the middle of the project and want to see
the effect on all of the tasks. Basically, what I want to do is show that
six-week gap across all tasks at once without having to go into each
individual task, split each task, adjust the dates for each task and have to
manually figure how much time would be remaining on each task (as I'm hoping
the software can do that for me). For example, task 40 would be, say, two
weeks into a total six week duration when the delay takes effect, making the
total duration now two weeks of the task already completed plus the six week
delay plus the remaining four weeks of activity that would remain after the
delay ends, for a total duration now of twelve weeks. Is there a simpler way
to show this on the project as a whole rather than have to split each
individual task? Thank you for any assistance you can provide.