J
Jaylene
Let's say I have a 40 hour task for a single resource that is supposed to
start on February 8. The resource is allocated 8 hours per day. As expected,
Project schedules the task to be completed 5 days later on February 12.
Let's say it's end of day Wednesday, February 10. My resource has made only
8 hours of progress since Monday. My remaining work is 32 hours, yet my
finish date still reflects February 12. How do i get my finish date to
reflect that there are 32 hours that remain from Wednesday? Reality says that
my resource will not finish 32 hours of work until the following Tuesday,
February 16.
start on February 8. The resource is allocated 8 hours per day. As expected,
Project schedules the task to be completed 5 days later on February 12.
Let's say it's end of day Wednesday, February 10. My resource has made only
8 hours of progress since Monday. My remaining work is 32 hours, yet my
finish date still reflects February 12. How do i get my finish date to
reflect that there are 32 hours that remain from Wednesday? Reality says that
my resource will not finish 32 hours of work until the following Tuesday,
February 16.