How do I remove tasks from EPM timesheets for completed projects?

R

Regina

For Project 2003 - I have projects that I have closed, have a status of
complete & inactive, and tasks that are 100% complete. The tasks are still
showing up on individual's EPM timesheets. What can I do so they do not show
up on the timesheets?
 
D

Dale Howard [MVP]

Regina --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question, do
the following:

1. Open a completed project.
2. Click Tools - Build Team from Enterprise.
3. Set the Booking value to Proposed for every enterprise resource on your
project team and then click the OK button.
4. Click Collaborate - Publish - All Information.
5. Close the project.

Hope this helps.
 
Top