How do I set milestone to 100% complete?

  • Thread starter Stanislav Gureyev
  • Start date
S

Stanislav Gureyev

I create milestones in the project plan by entering 0 into duration field. When all the activities are complete and I try to enter 100% complete on a milestone, the project server requests to sync the actuals and clears the progress on the milestone setting it to 0% complete. How can I make the Project Server retain 100% complete on a milestone

Regards
Stanislav Gureye
GRT Corporatio
 
D

Dale Howard [MVP]

Stanislav --

Microsoft has issued a hofix for this issue as referenced in KB832887. You
can download the hotfix at:

http://support.microsoft.com/default.aspx?scid=kb;en-us;832887&Product=OffPrServ2003

Hope this helps.




Stanislav Gureyev said:
I create milestones in the project plan by entering 0 into duration field.
When all the activities are complete and I try to enter 100% complete on a
milestone, the project server requests to sync the actuals and clears the
progress on the milestone setting it to 0% complete. How can I make the
Project Server retain 100% complete on a milestone?
 
S

Stanislav Gureyev

Thanks, Dave! That's exactly what we were looking for

Stanislav Gureye
GRT Corporation
 
D

Dale Howard [MVP]

Stanislav --

The name is Dale, not Dave, and you are certainly welcome! :)
 