I create milestones in the project plan by entering 0 into duration field. When all the activities are complete and I try to enter 100% complete on a milestone, the project server requests to sync the actuals and clears the progress on the milestone setting it to 0% complete. How can I make the Project Server retain 100% complete on a milestone
Regards
Stanislav Gureye
GRT Corporatio
Regards
Stanislav Gureye
GRT Corporatio