how do I set quarters to begin from project startdate?

M

Mike Glen

Hi w kuencer,

Welcome to this Microsoft Project newsgroup :)

You can't set it exactly to the date as quarters are related to the year
:( The bestyou can get is Format/Timescale... and in the dialog set the top
tier to Q1, Q2... (from start).

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP



wrote:
 