A
Alan Eisenberg
I need to set up an MS Project where multiple resources are working on the
same tasks, but in very different ways. For instance, I work on task A for 8
weeks, Danny works on it for 12 weeks. Paul works on it for 3 weeks. The task
will be gated by Danny especially since we do not collaborate - our
individual work is completely separate. I can only see how Project will
handle a task being reduced with mutiple resources. In our case, we cannot
work on eachother's parts.
I have set up the Project to show my tasks, Danny's tasks and Paul's tasks
separately with the same task names that are not linked in any way. But then
the task complete dates must be manually determined by he who works on it the
longest (assuming we all start at the same time). There's gotta be a better
way!
Alan Eisenberg
(e-mail address removed)
or (e-mail address removed)
same tasks, but in very different ways. For instance, I work on task A for 8
weeks, Danny works on it for 12 weeks. Paul works on it for 3 weeks. The task
will be gated by Danny especially since we do not collaborate - our
individual work is completely separate. I can only see how Project will
handle a task being reduced with mutiple resources. In our case, we cannot
work on eachother's parts.
I have set up the Project to show my tasks, Danny's tasks and Paul's tasks
separately with the same task names that are not linked in any way. But then
the task complete dates must be manually determined by he who works on it the
longest (assuming we all start at the same time). There's gotta be a better
way!
Alan Eisenberg
(e-mail address removed)
or (e-mail address removed)