Hi all
Just wondering if anyone could direct me to the area that I actually set up
the RBS in Project Server 2007.
I have sifted through the MS documentation but cant seem to find the 'how to
do it'.
Many thanks
Mardi
 
N

NZ Projects

The RBS is configured from PWA, Server Settings, Enterprise Custom Fields.

From this page you'll see the RBS custom field already exists, as does the
RBS lookup table.

You need to add values to the RBS lookup table, making sure the mask
reflects the levels within the table.

ie if your RBS will take the form

ORG
Location1
Dept1
Dept2
Location2
Dept1
Dept2

Then the mask for the table will be

Character
Character
Character

This reflects the depth (no of levels) in the RBS.

Hope this helps.
 