in Project 2003:
Tools / Change Working Time
Picklist for : slect the calendar you want to use (Standard by default)
Select the S and S columns
Click the Nondefault working time option (right side)
Click on the headers to select individual days (you can click and drag
to select more than 1) and then click "Nondefault working time".