How can I make weekends as work days in Project 2003?
G Gérard Ducouret Mar 25, 2009 #2 Hello, in Project 2003: Tools / Change Working Time Picklist for : slect the calendar you want to use (Standard by default) Select the S and S columns Click the Nondefault working time option (right side) Gérard Ducouret
Hello, in Project 2003: Tools / Change Working Time Picklist for : slect the calendar you want to use (Standard by default) Select the S and S columns Click the Nondefault working time option (right side) Gérard Ducouret
D Dave Mar 25, 2009 #3 D675 said: How can I make weekends as work days in Project 2003? Click to expand... Tools/Change Working Time Click on the headers to select individual days (you can click and drag to select more than 1) and then click "Nondefault working time".
D675 said: How can I make weekends as work days in Project 2003? Click to expand... Tools/Change Working Time Click on the headers to select individual days (you can click and drag to select more than 1) and then click "Nondefault working time".