How do I show a single resource usage

F

Fran

I am sure that Project used to display individual's time sheets, but all I
can find in 2007 is a resource usage report which has them all.

I cannot print selection, nor does it select date ranges very well (starts
at the date requested, but carried on for a year)
 
D

Dave

I suspect that the timesheets you saw may have been in Project Server.

If you want to display a single resource only in the Resource Usage view
then you will have to create a filter.
 