S
sc_p
I am using Project 2003 and it has got an annoying habit of splitting most
tasks with a duration of 1 day into 7 hours of work on one day and 1 hour of
work the following day when you look at them within the Resource Usage view.
This is mucking up my Gantt chart as the tasks effectively look as if they
are 2 day tasks (although the duration cell definitely says 1 day). Any idea
what is causing the problem and how do I fix it? Things to note:
- The project calendar and resource calendars are definitely showing 8 hour
working days (8-12 then 1-5) so that isn’t causing the problem.
- If I have a task with a duration of more than one day Project splits it so
that the first day is 7 hours, middle days are 8 hours, and there if a final
day of 1 hour, so it doesn’t seem to have a problem fitting in 8 hours days.
Thanks.
tasks with a duration of 1 day into 7 hours of work on one day and 1 hour of
work the following day when you look at them within the Resource Usage view.
This is mucking up my Gantt chart as the tasks effectively look as if they
are 2 day tasks (although the duration cell definitely says 1 day). Any idea
what is causing the problem and how do I fix it? Things to note:
- The project calendar and resource calendars are definitely showing 8 hour
working days (8-12 then 1-5) so that isn’t causing the problem.
- If I have a task with a duration of more than one day Project splits it so
that the first day is 7 hours, middle days are 8 hours, and there if a final
day of 1 hour, so it doesn’t seem to have a problem fitting in 8 hours days.
Thanks.