How do I sum.....

M

Mark

I have set up the column to be r=color RED, g =color GREEN, y = color YELLOW.
Basically Red = no started, Y = working, and Green = completed. I want to
sum all the field to determine percentage complete. So if all Green then
100% complete. If I have 10 fields and 5 are Green and 5 are either yellow
or red then total is 50%. How do I create that formula?
 
M

Mark

Peo -

Thanks, that is exaclty what I needed. Can you help me take it a step
further:

If I am less than 50% show red, between 50-99% show yellow and 100% show
green for the summed field.

Thanks!

Mark
 
D

Dave Peterson

Take a look at Format|Conditional formatting.

You'll see that you can specify up to 3 formats (which sounds perfect for you!).
 
Top