R
RonSo
I have already tried unchecking the tools/options/calculation/Updating task status updates resource status and actuals hours still changes when I update the task %complete. Here is the excerpt from the help file on this option that clearly implies this should not be happening:
************************************************************************************
Updating task status updates resource status Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration.
For example, if you update a task's percent complete, the % Complete field for the resource and assignment are automatically calculated to reflect that task's percent complete.
Selecting this check box also causes the reverse to be true: if you update resource status, then task status is automatically updated.
If this check box is cleared, you must enter values in the Actual Work field for resources in order to have an accurate picture of the actual work and actual cost. By default, this check box is selected.
Whether this check box is selected or cleared, once a task is 100 percent complete, work on assignments is also marked complete.
**********************************************************************************
I want actual hours, which are coming from the PWA timesheet, to remain unchanged if a TASK %complete is updated. How do I do that?
************************************************************************************
Updating task status updates resource status Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration.
For example, if you update a task's percent complete, the % Complete field for the resource and assignment are automatically calculated to reflect that task's percent complete.
Selecting this check box also causes the reverse to be true: if you update resource status, then task status is automatically updated.
If this check box is cleared, you must enter values in the Actual Work field for resources in order to have an accurate picture of the actual work and actual cost. By default, this check box is selected.
Whether this check box is selected or cleared, once a task is 100 percent complete, work on assignments is also marked complete.
**********************************************************************************
I want actual hours, which are coming from the PWA timesheet, to remain unchanged if a TASK %complete is updated. How do I do that?