I am having trouble viewing the Tracking Gantt chart in Project 2003 because
when I select that view I get an error message stating that: "The view or
report cannot be displayed because the table "Entry 1" on which it is based
has been deleted".

How do I resolve this issue and get to view my Tracking Gantt?

I look forward to hearing from you.

Kind regards,

Paul
 
D

Dale Howard [MVP]

Paul --

Open the project in question and click View - More Views. Select the
Tracking Gantt view and click the Edit button. In the Table pick list,
select the Entry table and then click OK. Click Apply to confirm that you
can now see this View.

If you are having this problem in every project, then continue by clicking
Tools - Organizer. Copy the Tracking Gantt view from the list on the right
(current project) to the list on the left (Global.mpt) and click Yes when
prompted to overwrite the View. Click the Close button, then save and close
the project and then exit Microsoft Project to save the Global.mpt file.
Hope this helps.
 