Showing baseline and actual/scheduled bars in a Gantt Chart

M

MalkiaSashko

Hello,

Basically, what I want to do is this: display two bars for each task i
the Gantt Chart view (or another view if this is not possible in th
Gantt Chart view) - the first bar showing the baseline and the secon
one the actual start/end dates of the tasks. Is this possible at all an
if yes - how?

Thank you very much in advance.

Cheer
 
D

Doctor Dave

MalkiaSashko said:
Hello,

Basically, what I want to do is this: display two bars for each task in
the Gantt Chart view (or another view if this is not possible in the
Gantt Chart view) - the first bar showing the baseline and the second
one the actual start/end dates of the tasks. Is this possible at all and
if yes - how?

Thank you very much in advance.

Cheers

In the first instance, look at the tracking Gantt.
 