How do I view past timesheet hours?

Z

Ztypical

I would like to be able to view what a resource has charged to a project over
the last few periods, but I only seem to be able to see what has been charged
in the current period. Any suggestions?
 
D

Dale Howard [MVP]

Ztypical --

You might try the View Resource Assignments page from the Resource Center
page for this purpose. Hope this helps.
 
Z

Ztypical

Thanks for responding.

It does not appear that time is shown in 'View Resource Assignments'
includes time reported during past periods. I see the 'View Resource
Availability' view, but that appears to show total Work, mixing both Actual
and Remaining. I would like to just see Actuals, by Resource, by project and
time period (preferably week/month).
 
D

Dale Howard [MVP]

Ztypical --

Click the "Timesheet Format" link in the sidepane on the left. Then click
the View Options tab and change the date Units value to Weeks. The
information you seek will be in the timesheet grid on the right on a week by
week basis. Hope this helps.
 
Top