Anya Langguth said:
Hi Mike,
arghghgh! so now I am back at the start again! So in fact it is not possible
to save custom data in to a baseline?? Trust me I have interrogated those
help pages!
So you are saying that what John said below is in fact incorrect?
I have actually given up on this and found another solution. What I was
trying to do was add a custom field called "investment" - which is an amount
of money that my company wishes to investment in a certain project. I wanted
to keep this "investment" money separate so that I could view in reports how
much of the total cost was in fact "investment" money.
I have now just added this investment money in to the Fixed Cost field for
the project and renamed the Fixed Cost to say "Investment". We don't have any
fixed costs here (we are a web design company) so I'm thinking that this will
work ok.
Thanks for the help and link - I will have a look.
cheers
anya
Anya,
Since you called my response into question I feel I must elaborate. I
thought Mike's clarification that Project's built-in Baseline fields
only apply to certain fields was adequate but apparently not. I
neglected to point that out when I said, "Baseline fields in Project are
simply a snapshot of the field they are saving at a specific point in
time". However, a "baseline" by definition is a snapshot of data at a
point in time. Project has specific built-in baseline fields but a
"baseline field" does not need to be limited to the built-in one. From
the description of your "investment" cost, you can still save a
baseline. It just won't be a built-in baseline and to set it will
require a manual operation NOT activated by the menu,
"Tools/Tracking/Save Baseline".
I agree with Steve and further believe you may actually be "double
dipping" by using the Fixed Cost field for your investment cost. You
indicate your investment cost is made up of the built-in Cost field plus
Cost1. Fixed Costs are added to the Cost field, so if you are still
using the additive formula for investment cost, you are doubling the
value.
Why not simply do as I suggested in the first place, although I probably
wasn't specific or clear enough. Create a custom field (e.g. Cost2) that
adds Cost and investment (i.e. Cost1). Since this value will vary as
Cost varies, in order to "save a baseline", copy the contents of Cost2
into a third custom field (e.g. Cost3) called "investment baseline".
This then takes a snapshot of of the summed up investment cost at a
point in time (whenever the copy was executed).
Hopefully this clears a few thing up.
John