I have a completed project, and would like to close it off without losing all
the "actual" data that's been gathered on the server.
By "closing it off" I hope to prevent people from submitting time against
the plan, and--ideally--to remove any of this plan's tasks from everyone's
timesheets.
We've tried setting all tasks to 0 Remaining Work and 0 Remaining Duration,
being careful to ensure that all tasks were 100% complete (we had to manually
make the milestones 100% complete) and that the project as a whole was 100%
complete.
But this left tasks with non-zero "Remaining Work" on some resources'
timesheets.
We also don't want to use the options in "Clean up Project Server" because
we'd lose our actual data from the server.
the "actual" data that's been gathered on the server.
By "closing it off" I hope to prevent people from submitting time against
the plan, and--ideally--to remove any of this plan's tasks from everyone's
timesheets.
We've tried setting all tasks to 0 Remaining Work and 0 Remaining Duration,
being careful to ensure that all tasks were 100% complete (we had to manually
make the milestones 100% complete) and that the project as a whole was 100%
complete.
But this left tasks with non-zero "Remaining Work" on some resources'
timesheets.
We also don't want to use the options in "Clean up Project Server" because
we'd lose our actual data from the server.