hosealtx,
Pretty simple. Go to Window/Split. In the upper pane display the
Resource Sheet and in the lower pane display the Gantt Chart. Be advised
though that the Gantt will display the full task duration, not just the
selected resource assignment (if they are different).
Hope this helps.
John
Project MVP