T
tennisne1
I need to create a project plan that will list the actual start, actual end,
estimated start, estimated end, total days between the actual start and
actual end, and the total days between estimated start and estimated end. I
need to know how I can customize the total actual days and total estimated
days. I want two values on the project plan that compare what the estimated
days for the task was and what the actual amount of days the task actually
took to complete the task. I tried customizing my own days columns, but
everytime I try to calculate a datediff on actual start and actual end or
baseline start and baseline end, the value ends up as 0.01! It does not
calculate the total days. How do you do this in Project 2003? I basically
need two representations of durations...one for actual and one for original
estimate. Thanks.
estimated start, estimated end, total days between the actual start and
actual end, and the total days between estimated start and estimated end. I
need to know how I can customize the total actual days and total estimated
days. I want two values on the project plan that compare what the estimated
days for the task was and what the actual amount of days the task actually
took to complete the task. I tried customizing my own days columns, but
everytime I try to calculate a datediff on actual start and actual end or
baseline start and baseline end, the value ends up as 0.01! It does not
calculate the total days. How do you do this in Project 2003? I basically
need two representations of durations...one for actual and one for original
estimate. Thanks.