how do you do schedule compression in microsoft project?

Q

QTW2005

I am trying to compress a schedle by two days. I know how to do this by
hand, but not using MS Project. Does any one kno how?

Thank you,
 
R

Reiner Kuehn

Hi,
project is just a tool - it does not take away the work for optimizing the
schedule from you.

In general, to shorten the project focus on reducing the duration of the
(longest) tasks on the critical path.

This rule is tool independent...

Regards,
Reiner
 