How do you include a custom field in a time scaled data report

W

Wina.WW

Hi There,

Does anyone know how to include a custom field in a time scaled data report?
I created a custom field, (text 8 = Projects) to organize my tasks by
projects, similar to organizing task by dept.. I would like to see actual
work organized by the projects. Is there a way I need to organize my project
plan for me to collect this data?

Thank you,
Wina
 
M

Marc Soester [MVP]

Hi Wina,

If I understand your question corerrectly, you wish to have a time phases
custom field simular to work or cost?

Unfortunalty Custom fields are not "assignment" fields and therefore cannot
be made timephased. You can however group and filter custome fields and
display exisitng timephased data like cost and work.
I hope that helps
 
Top