M
Mike
Hello,
If I add a resource by typing in some new initials in the Gantt view,
then go to resource sheet view, I have to change the base calendar for
the new resource to whatever calendar I am currently using for the
project. Is there a way of specifying that all new resources will use
a particular non-standard calendar when you add them?
thanks,
Mike
If I add a resource by typing in some new initials in the Gantt view,
then go to resource sheet view, I have to change the base calendar for
the new resource to whatever calendar I am currently using for the
project. Is there a way of specifying that all new resources will use
a particular non-standard calendar when you add them?
thanks,
Mike