How I level resources based Day by Day Setting (Project)?

C

Cleber

On the resourse sheet of Microsof Project, an attention simbol is displayed
next to a resourse and the resourse highlights in red. The help box says:
"This resourse must be leveled on day by day setting". Please tell me how I
can level a resource on a day by day setting.

Best Regards
 
M

Mike Glen

Hi Cleber,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Level Resources.../Look for overallocations on a - select Day by
Day from the pick list.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
Top