How to add a column in PWA

R

Robert

Hello,
How can I add the "Duration" field in the left pane of the Timesheet of PWA
2002 ?
Thanks in advance,

Robert
 
D

Dale Howard [MVP]

Robert --

Every project manager will need to open EVERY project and do the following:

1. Click Tools - Customize - Published Fields
2. Select the Duration field and copy it to the list on the right
3. Click the Set as Default button
4. Click OK
5. Click Collaborate - Publish - Republish Assignments and then click OK

Step 5 will "push" the Duration column to each users timesheet. Do know,
however, that team members cannot edit the Duration value in PWA. Hope this
helps.
 
Top