P
PedroJose
I need to add a field to the general My Timesheet view in PR2007. The
purpose is to allow resources to report their estimated %complete for a task
right on the timesheet (not the % complete calculated by Project). Then I
need that value (which should be required) to flow through My Tasks during
the timesheet import process and then flow to the Project Plan (in project
professional) after approval and submission. Basically I can then create a
field to calculate the delta between the project calculated % Comp. and the
resource reported % Comp.
I have inserted a field (number type) and it appears in the timesheet but it
is not required (although I have made a required field in the custom field
definition server settings option) and it does not flow through.
Can anyone help?
purpose is to allow resources to report their estimated %complete for a task
right on the timesheet (not the % complete calculated by Project). Then I
need that value (which should be required) to flow through My Tasks during
the timesheet import process and then flow to the Project Plan (in project
professional) after approval and submission. Basically I can then create a
field to calculate the delta between the project calculated % Comp. and the
resource reported % Comp.
I have inserted a field (number type) and it appears in the timesheet but it
is not required (although I have made a required field in the custom field
definition server settings option) and it does not flow through.
Can anyone help?