S
scottsoo9
I have a spreadsheet from excel with numbers such as start and end date
% complete, % funds expended, hours expended, dollars authenticated, an
dollars expended, travel costs, subcontractor costs, and amount invoice
and amount paid but with no actual resources. I need to put this int
project.
My problem besides being relatively new to project is that I do no
know how to put that data in without supplying the actual resources i
the resource sheet. (which i do not have) I can do things such as star
and end date, and percent complete but after that it gets much mor
challenging for me. Any guidance on how I would go about doing thi
would be greatly appreciated.
Thanks, Scot
% complete, % funds expended, hours expended, dollars authenticated, an
dollars expended, travel costs, subcontractor costs, and amount invoice
and amount paid but with no actual resources. I need to put this int
project.
My problem besides being relatively new to project is that I do no
know how to put that data in without supplying the actual resources i
the resource sheet. (which i do not have) I can do things such as star
and end date, and percent complete but after that it gets much mor
challenging for me. Any guidance on how I would go about doing thi
would be greatly appreciated.
Thanks, Scot