How to assign all tasks to a specific calendar?

R

Russel

I have a couple of calendars setup in project server. I see you can assign a
task to a calendar. But how do I assign all the tasks to a specific calendar
that I choose.
 
D

Dale Howard [MVP]

Russel --

Click Project - Project Information and set the Calendar value to the
calendar you wish, then click OK. Doing so will schedule all tasks in the
project using the calendar you select. Hope this helps.
 