How to automtilally assign tasks execution order

  • Thread starter Sebastián Streiger
  • Start date
S

Sebastián Streiger

Hi:
I´m new to Project and I´m having trouble in organizing the tasks assigned to a resource.
The tasks are no linked, I mean there is no NEED to finish task A before beggining task B. But I want them to start in that order.
Both tasks are assigned to the same resource and require 100% dedication so the should not overlap.
I´d like task B to move back and fordward, depending of the delays or advances in task A.
This is a simple example but there are a lot more task in this situation.
How could I model this?

Thanks in advance
 
S

Sebastián Streiger

I just would like to add, that I want the task to reassign its start date If I change the resource that will perform it.

Thanks in advance

--
Sebastián Streiger
Unisolutions S.A.
[email protected]

"Sebastián Streiger" <[email protected]> escribió en el mensaje Hi:
I´m new to Project and I´m having trouble in organizing the tasks assigned to a resource.
The tasks are no linked, I mean there is no NEED to finish task A before beggining task B. But I want them to start in that order.
Both tasks are assigned to the same resource and require 100% dedication so the should not overlap.
I´d like task B to move back and fordward, depending of the delays or advances in task A.
This is a simple example but there are a lot more task in this situation.
How could I model this?

Thanks in advance
 
S

Sebastián Streiger

Al:
Many thanks for your advice. I added the priority column and now the
task are getting aligned the way I needed.
I´ll see how it will work when I have to do the follow-up.

Thank you very much
 