Sebastián Streiger
Hi:
I´m new to Project and I´m having trouble in organizing the tasks assigned to a resource.
The tasks are no linked, I mean there is no NEED to finish task A before beggining task B. But I want them to start in that order.
Both tasks are assigned to the same resource and require 100% dedication so the should not overlap.
I´d like task B to move back and fordward, depending of the delays or advances in task A.
This is a simple example but there are a lot more task in this situation.
How could I model this?
Thanks in advance
I´m new to Project and I´m having trouble in organizing the tasks assigned to a resource.
The tasks are no linked, I mean there is no NEED to finish task A before beggining task B. But I want them to start in that order.
Both tasks are assigned to the same resource and require 100% dedication so the should not overlap.
I´d like task B to move back and fordward, depending of the delays or advances in task A.
This is a simple example but there are a lot more task in this situation.
How could I model this?
Thanks in advance