I'm interested as to how people handle contractor billing in Project Server.
Currently (not Project Server), we estimate an external resource cost based
on what we know about tasks. When contractor invoices arrive, they are
billed to the project and taken from that "external resource" bucket.
I see 2 options with Project Server
1) Define each contractor in Project Server and calculate an actual hourly
rate, track tasks as normal and then match this cost against invoices when
they arrive. this requires contracts to have access to Project Server to log
time.
2) Bill contractors at $0.00 p/h (either local resources or a generic
resource) and only enter in the invoiced cost when it comes in fortnightly.
This would mirror our current approach.
I'd like the approach which means the least overhead for the PM, but also
doesn't skew budget data. I'm also concerned about paying for lots of CAL's
for contractors to have access to log time.
Any suggestions?
Currently (not Project Server), we estimate an external resource cost based
on what we know about tasks. When contractor invoices arrive, they are
billed to the project and taken from that "external resource" bucket.
I see 2 options with Project Server
1) Define each contractor in Project Server and calculate an actual hourly
rate, track tasks as normal and then match this cost against invoices when
they arrive. this requires contracts to have access to Project Server to log
time.
2) Bill contractors at $0.00 p/h (either local resources or a generic
resource) and only enter in the invoiced cost when it comes in fortnightly.
This would mirror our current approach.
I'd like the approach which means the least overhead for the PM, but also
doesn't skew budget data. I'm also concerned about paying for lots of CAL's
for contractors to have access to log time.
Any suggestions?