Hi all,

Is it possible to change the project calendar from one enterprise calendar
to another enterprise calendar?

Thanks, Simon
 
G

Gérard Ducouret

Simon,
If you created a specific calendar in the Enterprise Global, you can assign
this calendar to any project:
Project / Project information / Calendar...

Gérard Ducouret
 
R

Rubost So

Thanks Gérard Ducouret,

But I cannot find the new added enterprise calendar in Project / Project
information / Calendar...

Any idea?
 
G

Gérard Ducouret

Simon,
If you created this new calendar right now in the Enterprise global, you
have to close Project, then to reopen it, so that it takes in account the
new Enterprise Global.

Gérard Ducouret
 
S

SS

Thanks Gérard Ducouret,

The project calendar has been changed. But the new calendar seems not take
effect. Any idea?

Thanks again, Simon
 
S

SS

Hi all,

Let me elaborate the situation:
I have changed the project calendar from one Enterprise Calendar to another
Enterprise Calendar;
I can see the change via Tools > Change Working Time;
However, in the Resource Graph view, the change is not taken effect.

Any one can help?

Thanks, Simon
 
G

Gérard Ducouret

Simon,
In the enterprise Resource Pool, did you assigned the new calendar on each
resource?
If not, they are still working with the old calendar

Gérard Ducouret
 