how to change finish and start fields format?

  • Thread starter Porfirio Fuentes
  • Start date
P

Porfirio Fuentes

Hi, I think I saw somwhere in the PWA an option to change the date format, but I dont remember where, anyway, I'm not sure if that's the solution for my requirement.

I just want the start and finish dates in PWA, to show only the date and not the date and time, is it possible?, how?

TIA

Porfirio Fuentes
 
D

Dale Howard

Porfirio --

The date format can be changed to show the date only (without the time) on
the View My Tasks page, the Resource Center page, the View Resource
Assignments page, and the Updates page.

The date format CANNOT be changed on either the Project Center page or the
detailed Project page, which is probably where you want to change the date
format. Sorry for the bad news. Hope this helps.




Porfirio Fuentes said:
Hi, I think I saw somwhere in the PWA an option to change the date format,
but I dont remember where, anyway, I'm not sure if that's the solution for
my requirement.
I just want the start and finish dates in PWA, to show only the date and
not the date and time, is it possible?, how?
 