How to display costs by resource group on Recapitulative tasks

D

dscemama

Hi,

My software development project has five main recapitulative tasks. I need
to know for each one of them what is the cost by resource group.

When I use the task usage display (adding the cost and resource group
column) and filter using a group, the cost displayed on the recap tasks are
still total costs.

Thanks
 
J

JulieS

Hello,

Instead of filtering, apply a group to the Task Usage view. Group
first by ID or Name, then by Resource Group. Grouping summarizes
data from fields visible in the table.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

dscemama

If I do so, I have a list of all my tasks and for every task the cost for
each resource group.
But there is no task hierarchy, they are all there (thousands), ordered by
name and it's useless since I only need the five main recapitulative tasks.

Is there a way to keep the task hierarchy ?
 
J

JulieS

Try grouping by Outline Number then Resource Group (Assignment
field). The show only level 2 -- that should collapse up to summary
level tasks and each group should be represented once.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top